Project Overview

SMO (Scavenger Mining Operation) — Mechanical & Piping Installation

Completion of the Scavenger Mining Operation (SMO) plant project, managing the supply chain for all necessary components. Scope included: manufacturing, delivering, assembling and testing two cutter suction dredgers (150 tph CSD 200) and one process water pump (Godwin CD250M); supply and installation of a screening module with feed bin, vibrating screen, transfer sump and pumps; and implementing two 150 tph spiral plants and overland piping per Kenmare's specifications.

The Challenge

Coordinating long-lead mechanical packages, spiral plant installation and overland piping into a tight delivery window on a live mining operation.

Our Solution

Integrated supply-chain management combined with on-site mechanical and piping execution under a single accountable contract.

The Outcome

Project completed exceeding 50,000 LTI-free hours.

Project Details

Client
Kenmare Resources plc
Location
Moma Mine, Nampula Province, Mozambique
Sector
Mining
Disciplines
mechanical piping structural
Project Period
Apr 2024 – Jul 2025